Everything about 7 World Trade Center totally explained
7 World Trade Center is a building in
New York City located across from the
World Trade Center site in
Lower Manhattan. The name "7 World Trade Center" has referred to two buildings: the original structure, completed in 1987, and the current structure. The original building was destroyed on
September 11, 2001 and replaced with the new 7 World Trade Center, which opened in 2006. Both buildings were developed by
Larry Silverstein, who holds a
ground lease for the site from the
Port Authority of New York and New Jersey.
The original 7 World Trade Center was 47 stories tall, clad in red exterior masonry, and occupied a
trapezoidal footprint. An elevated walkway connected the building to the
World Trade Center plaza. The building was situated above a
Consolidated Edison (Con Ed) power substation, which imposed unique structural design constraints. When the building opened in 1987, Silverstein had difficulties attracting tenants. In 1988,
Salomon Brothers signed a long-term lease, and became the main tenants of the building. On
September 11,
2001, the WTC7 was damaged by
debris when the nearby North Tower of the WTC
collapsed. Its structural integrity was further compromised by fires that burned throughout the afternoon and the building collapsed completely at 5:20 p.m. Investigators are currently trying to determine exactly how the combination of local structural damage and fire caused the collapse of the whole structure. A final report is expected in or after July 2008.
The new 7 World Trade Center construction began in 2002 and was completed in 2006. It is 52 stories tall and still situated above the aforementioned power substation. Built on a smaller footprint than the original to allow
Greenwich Street to be restored from
TriBeCa through the World Trade Center site and south to
Battery Park, the new building is bounded by
Greenwich,
Vesey,
Washington, and
Barclay streets. A small park across Greenwich Street occupies space that was part of the original building's footprint. The current 7 World Trade Center's design placed emphasis on safety, with a
reinforced concrete core, wider stairways, and thicker fireproofing of steel columns, and incorporates numerous
environmentally friendly features.
1983–2001
The original 7 World Trade Center was a 47-story building, designed by
Emery Roth & Sons, with a red
granite façade. The building was 610 feet (186 m) tall, with a
trapezoidal footprint that was 330 ft (101 m) long and 140 ft (43 m) wide.
Tishman Realty & Construction managed construction of the building, which began in 1983.
The substation had a
caisson foundation designed to carry the weight of a future building of 25 stories containing 600,000 sq ft (55,700 m²).
The structural design of 7 World Trade Center included features to allow a larger building than originally planned to be constructed. A system of gravity column transfer trusses and girders was located between floors 5 and 7 to transfer loads to the smaller foundation. The spray-on
fireproofing for structural steel elements was
gypsum-based
Monokote which had a two-hour fire rating for steel beams, girders and truss, and a three-hour rating for columns. Fuel oil distribution components were located at ground level, up to the ninth floor. After the
World Trade Center bombings of
February 26,
1993, New York City mayor
Rudy Giuliani decided to situate the emergency command center and associated fuel tanks at 7 World Trade Center. Although this decision was criticized in light of the events of
9/11, the fuel in the building is today not believed to have contributed to the collapse of the building. The roof of the building included a small west penthouse and a larger east mechanical penthouse.
In all, 7 World Trade Center had 1,868,000 sq ft (174,000 m²) of office space. Two pedestrian bridges connected the main World Trade Center complex, across Vesey Street, to the third floor of 7 World Trade Center. The lobby of 7 World Trade Center had three murals by artist
Al Held:
The Third Circle,
Pan North XII, and
Vorces VII. A sculpture by
Alexander Calder, called
WTC Stabile (also known by other names,
The Cockeyed Propeller and
Three Wings) was on a plaza in front of the building.
Tenants
In June 1986, before construction was completed, Silverstein signed
Drexel Burnham Lambert as a tenant to lease the entire 7 World Trade Center building for $3 billion over a term of 30 years.
In December 1986, after the
Boesky insider-trading scandal, Drexel Burnham Lambert canceled the lease, leaving Silverstein to find other tenants.
Spicer & Oppenheim agreed to lease 14 percent of the space, but for more than a year, as
Black Monday and other factors adversely affected the
Lower Manhattan real estate market, Silverstein was unable to find tenants for the remaining space. By April 1988, Silverstein had lowered the rent and made other concessions.
In November 1988,
Salomon Brothers withdrew from plans to build a large new complex at
Columbus Circle in
Midtown and agreed to a 20-year lease for the top 19 floors of 7 World Trade Center.
The building was extensively renovated in 1989 to accommodate the needs of Salomon Brothers.
Most of three existing floors were removed as tenants continued to occupy other floors, and more than 350 tons (U.S.) of steel were added to construct three double-height trading floors. Nine diesel generators were installed on the 5th floor as part of a backup power station. "Essentially, Salomon is constructing a building within a building - and it's an occupied building, which complicates the situation," said a district manager of
Silverstein Properties. The unusual task was possible, said
Larry Silverstein, because it was designed to allow for "entire portions of floors to be removed without affecting the building's structural integrity, on the assumption that someone might need double-height floors."
Collapse
As the North Tower collapsed on
September 11,
2001, debris hit 7 World Trade Center, causing heavy damage to the south face of the building.
After the North Tower collapsed, some firefighters entered 7 World Trade Center to search the building. They attempted to extinguish small pockets of fire, but low water pressure hindered their efforts. A massive fire burned into the afternoon on the 11th and 12th floors of 7 World Trade Center, the flames visible on the east side of the building. During the afternoon, fire was also seen on floors 6–10, 13–14, 19–22, and 29–30. During the afternoon, firefighters also heard creaking sounds coming from the building. Around 3:30 pm FDNY Chief Daniel Nigro decided to halt rescue operations, surface removal, and searches along the surface of the debris near 7 World Trade Center and evacuate the area due to concerns for the safety of personnel. The investigation, led by Dr S. Shyam Sunder, drew not only upon in-house technical expertise, but also upon the knowledge of several outside private institutions, including the Structural Engineering Institute of the
American Society of Civil Engineers (SEI/ASCE), the
Society of Fire Protection Engineers (SFPE), the
National Fire Protection Association (NFPA), the American Institute of Steel Construction (AISC), the
Council on Tall Buildings and Urban Habitat (CTBUH), and the
Structural Engineers Association of New York (SEAoNY).
NIST has released a video and still-photo analysis of 7 World Trade Center before its collapse that appears to indicate a greater degree of structural damage from falling debris than originally assumed by FEMA. Specifically, NIST's interim report on 7 World Trade Center displays photographs of the southwest façade of the building that show it to have significant damage. The report also highlights a 10-story gash in the center of the south façade, toward the bottom, extending approximately a quarter of the way into the interior. Consistent with this theory, news footage shows cracking and bowing of the building's east wall immediately before the collapse, which began at the penthouse floors.
A progress report was released in June 2004, outlining NIST's working hypothesis. NIST is utilizing
ANSYS to model events leading up to collapse initiation and
LS-DYNA models to simulate the global response to initiating events. According to NIST, the investigation of 7 World Trade Center has been delayed for a number of reasons, including that NIST staff who had been working on 7 World Trade Center were assigned full-time from June 2004 to September 2005 to work on the investigation of the collapse of the twin towers. In June 2007, Shyam Sunder explained, "We are proceeding as quickly as possible while rigorously testing and evaluating a wide range of scenarios to reach the most definitive conclusion possible. The WTC 7 investigation is in some respects just as challenging, if not more so, than the study of the towers. However, the current study does benefit greatly from the significant technological advances achieved and lessons learned from our work on the towers."
Conspiracy theorists believe the building collapses on September 11, including that of
building seven, were the result of
controlled demolition. NIST states it has "found no evidence of a blast or controlled demolition event". In its final report on building 7, it would "like to determine the magnitude of hypothetical blast scenarios that could have led to the structural failure of one or more critical elements". The adjacent
Verizon Building, an
art deco building constructed in 1926, had extensive damage to its east façade from the collapse of 7 World Trade Center, though was able to be restored at a cost of US$1.4 billion.
Rebuilding 7 World Trade Center
Design
The new 7 World Trade Center has 52 stories and is 741 ft (226 m) tall. The building has 42 floors of leasable space, starting at the 11th floor, and a total of 1,700,000 sq ft (158,000 m²) of office space. The first ten floors house an electrical substation, which provides power to much of Lower Manhattan. The office tower has a narrower footprint at ground level than its predecessor so the course of Greenwich Street could be restored in an effort to reunite
TriBeCa and the
Financial District. To enclose the power substation and improve its aesthetics, the base of the building has a curtain wall with
stainless steel louvers that provide ventilation for the machinery. During the day, the curtain wall reflects light, while at night it illuminates with blue
LED lights. The curtain wall around the lobby uses heavily laminated, heat-strengthened glass that meets high standards for blast resistance. At night, a large cube of light above the lobby also emanates blue light, while during the day it provides white light to the lobby, and at dusk it transitions to violet and back to blue. Inside the main lobby, artist
Jenny Holzer created a large light installation with glowing text moving across wide plastic panels.
The building is being promoted as the safest skyscraper in the U.S. According to Silverstein Properties, the owner of the building, it "will incorporate a host of life-safety enhancements that will become the prototype for new high-rise construction". The building has 2 ft (60 cm) thick
reinforced-concrete and
fireproofed elevator and stairway access shafts. The original building used only
drywall to line these shafts. The stairways are wider than in the original building to permit faster egress.
7 World Trade Center is equipped with
Otis destination elevators. After pressing a destination floor number on a lobby keypad, passengers are grouped and directed to specific elevators that will stop at the selected floor (there are no buttons to press inside the elevators). This system is designed to reduce elevator waiting and travel times. The elevator system is integrated with the lobby turnstile and card reader system that identifies the floor on which a person works as he/she enters and can automatically call the elevator for that floor.
In conjunction with Scott Chrisner of Chrisner Group, Tishman supported the LEED gold status for 7 World Trade Center in the U.S. Green Building Council's
Leadership in Energy and Environmental Design (LEED) program. The certification will name 7 World Trade Center New York City's First ‘Green’ Office Tower. Nearly 30 percent of structural steel used in the building consists of recycled steel. Rainwater is collected and used for irrigation of the park and to cool the building.
Construction
Tishman Construction Corporation of New York began work at the new 7 World Trade Center in 2002, soon after the site was cleared of debris. Restoring the Con Ed
electrical substation was an urgent priority to meet power demands of Lower Manhattan. Because 7 World Trade Center is separate from the main 16 acre (6.5 ha)
World Trade Center site,
Larry Silverstein required approval only from the
Port Authority and rebuilding was able to proceed quickly. Building Seven wasn't included in the original World Trade Center master plan by
Daniel Libeskind, but was designed by
Skidmore, Owings & Merrill under the leadership of David Childs, who largely
redesigned the
Freedom Tower.
Once construction of the power substation was complete in October 2003, work proceeded on building the office tower. An unusual approach was used in constructing the building; erecting the steel frame before adding the concrete core. This approach allowed the construction schedule to be shortened by a few months. Construction was completed in 2006 at a cost of $700 million. Though Silverstein received $861 million from insurance on the old building, he'd $400 million remaining in mortgage to pay off. Costs to rebuild were covered by $475 million in
Liberty Bonds, which provide tax-exempt financing to help stimulate rebuilding in Lower Manhattan and insurance money that remained after other expenses.
A 15,000 sq ft (1,400 m²) triangular park was created between the extended Greenwich Street and West Broadway by David Childs with Ken Smith and his colleague, Annie Weinmayr, of Ken Smith Landscape Architect. The park comprises an open central plaza with a fountain and flanking groves of
sweetgum trees and
boxwood shrubs. As the seasons change, so will the colors in the park, providing a natural complement to the tower. At the center of the fountain, sculptor
Jeff Koons created
Balloon Flower (Red), whose mirror-polished stainless steel represents a twisted balloon in the shape of a flower.
Building opened
The building was officially opened at noon on
May 23,
2006, with a free concert featuring
Suzanne Vega, Citizen Cope, Bill Ware Vibes, Brazilian Girls, Ollabelle,
Pharaoh's Daughter,
Ronan Tynan (of the
Irish Tenors), and special guest
Lou Reed. Prior to opening, in March 2006, the new 7 World Trade Center frontage and lobby were used in scenes for the movie
Perfect Stranger with
Halle Berry and
Bruce Willis.
Since the building opened, several unleased upper floors have been used for events such as charity lunches, fashion shows, and black-tie galas. Silverstein Properties allowed space in the new building to be used for these events as a means to draw people to see the building. From
September 8 to
October 7,
2006, the work of photographer Jonathan Hyman was displayed in "An American Landscape", a free exhibit hosted by the
World Trade Center Memorial Foundation at 7 World Trade Center. The photographs captured the response of people in New York City and across the
United States after the
September 11,
2001, attacks. The exhibit took place on the 45th floor while the space remained available for lease.
As of March 2007, 60 percent of the building had been leased. In September 2006,
Moody's signed a 20-year lease to rent 15 floors of 7 World Trade Center. Other tenants that had signed leases in 7 World Trade Center, as of May 2007, include
ABN Amro,
Ameriprise Financial Inc., Darby & Darby P.C., Mansueto Ventures LLC, business publisher of
Fast Company and
Inc., and the
New York Academy of Sciences.
The space occupied by Mansueto Ventures has been designed to use the maximum amount of natural light and has an open floor plan. The space used by the
New York Academy of Sciences on the 40th floor, designed by H
3 Hardy Collaboration Architecture, works with the parallelogram shape of the building. Keeping with the green design of the building, the NYAS uses recycled materials in many of the office furnishings, has zoned heating and cooling, and lights that detect motion, coming on automatically only when people are present, and adjust according to incoming sunlight.
Silverstein Properties also has offices in 7 World Trade Center, along with office space used by the architectural and engineering firms working on the
Freedom Tower,
150 Greenwich Street,
175 Greenwich Street, and
200 Greenwich Street. As of July 2007, space remains available on the ten uppermost floors and floors 35 through 37 of 7 World Trade Center.
Further Information
Get more info on '7 World Trade Center'.
|
External Link Exchanges
Do you know how hard it is to get a link from a large encyclopaedia? Well we're different and will prove it. To get a link from us just add the following HTML to your site on a relevant page:
<a href="http://7_world_trade_center.totallyexplained.com">7 World Trade Center Totally Explained</a>
Then simply click through this link from your web page. Our crawlers will verify your link, extract the title of your web page and instantly add a link back to it. If you like you can remove the words Totally Explained and embed the link in article text.
As long as your link remains in place, we'll keep our link to you right here. Please play fair - our crawlers are watching. Your site must be closely related to this one's topic. Any kind of spamming, dubious practises or removing the link will result in your link from us being dropped and, potentially, your whole site being banned. |